Our weekly update to residents regarding the ongoing work being carried out on our extensive road network by our grader teams is back for another week.
Don't forget to let us know if you see a road issue! You can report an issue by using the 'Snap Send Solve' app (available for iOS and Android), via www.yarriambiack.vic.gov.au, or by calling Customer Service on #03 5398 0100.
Northern Grader Teams
P126 &
P122 - Combined grader teams completed grading works on Phitzner Eys Road and Rainbow Wyperfeld Park Road.
P121 &
P123 - Combined grader teams completed grading works on Wardles West Road and Goads Lane.
Central Grader Teams
P120 - Commenced grading works on Pullens Road and Alisa Wheat Road.
P124 - Completed grading works on Mellis Road. Commenced grading works on Mount Pleasant Road.
Southern Grader Teams
P125 &
P127 - Combined grader teams completed grading works on the edges of Minyip Roch Avon Road and the edges of Banyena Pimpinio Road.